Industrial site readiness: support marketing with evidence
Examine the evidence behind industrial-site claims about pads, usable land, access, utilities, and due diligence. Prepare a research table that can improve the accuracy of a site-marketing draft.
What you will make
A site-claim evidence table and a short marketing-copy revision showing supported claims and unresolved questions.
A location map or attractive brochure does not establish buildable acreage, usable access, available utility capacity, or a readiness designation.
- Distinguish site-marketing statements from documented physical and infrastructure conditions.
- Identify evidence needed to investigate pads, access, utilities, and environmental conditions.
- Revise copy without inventing usable acreage, capacity, certification, or as-built conditions.
Before you start
- Use public records or instructor-supplied site materials approved for the project.
- Record missing technical documents as unavailable. Obtain instructor approval before requesting information from clients or providers.
Project connections: Red Onion industrial-site website and marketing.
Work through the method
List the proposed site claims
Select up to five statements from supplied material, such as available pad area, highway access, water service, electrical service, or readiness status. Record each statement verbatim with its source and date. Do not assume that Red Onion has any of these conditions because they appear in this exercise.
Check your work: The table separates supplied claims from facts independently established.
Investigate the land and pad
Seek a dated boundary or topographic survey, relevant geotechnical information, and a constraints map. Distinguish total parcel acreage from usable pad area. Record area units and the document's definition of usable land. Aerial imagery can help locate questions but cannot establish finished grading or as-built conditions.
Check your work: Any acreage or pad statement has an identified technical source, or remains unresolved.
Investigate usable access and utilities
Check access routes and utility documentation. For roads, distinguish mapped proximity from usable access and required improvements. For utilities, seek provider evidence of service location, capacity for the proposed demand, extension needs, cost, and timing. Record feet, miles, gallons per day, kilowatts, or other units exactly as the source gives them.
Check your work: Nearby infrastructure is not reported as confirmed available service or capacity.
Check due diligence and readiness evidence
Use VEDP's July 2026 characterization guidance to organize the review. Seek an actual characterization report and confirming designation record before repeating a tier claim. EPA's assessment guidance explains professional Phase I and possible Phase II work; a student source review does not establish contamination status or environmental clearance.
Check your work: The table distinguishes a document found, a finding it supports, and a missing assessment.
Revise a small piece of marketing copy
Create columns for claim, supporting record, date, units, evidence limit, and next confirmation. Rewrite a short paragraph using only supported findings. Keep unresolved items out of affirmative marketing statements and list them for instructor review. Publication remains a separate approved action.
Check your work: The revised paragraph makes no unsupported readiness, design, capacity, or as-built claim.
Optional practice: review five site-marketing claims
- Select up to five claims from instructor-approved site material.
- Connect each claim to a technical or administrative record and record its date and units.
- Identify missing evidence for usable pad area, access, utilities, and due diligence.
- Rewrite one marketing paragraph and prepare questions for instructor review. This optional practice is not a class grade or official Canvas assignment and does not authorize publication.
Bring the method into a product
- Site-claim evidence table
- Revised marketing paragraph
- Unresolved-document and confirmation list
Suggested formats: CSV, PDF, DOCX.
Reflect: Which attractive marketing statement became less certain when you examined the supporting record, and how did you revise it?
Avoid these mistakes
- Reporting gross parcel acreage as usable pad acreage.
- Treating a nearby road or utility line as proof of usable access or available capacity.
- Assigning a readiness tier or claiming engineered, as-built, or environmentally cleared conditions without the appropriate records.
Check your understanding
These short checks are practice, not course grades. Read the explanation, revise your reasoning and try again when useful.
Submit your practice product
Use the existing course login. Your file and notes are visible to you and the instructor, not the public or other students. Official graded assignments still go to Canvas.
Submit a PDF, image, DOCX, UTF-8 text/CSV, JSON or GeoJSON file. For several products, combine the evidence, text alternatives and notes into one accessible PDF or DOCX, or submit each file separately with the same project title. Keep native ArcGIS projects and complete shapefile bundles locally. Upload only work you can share with the instructor; leave out confidential client records and sensitive species or infrastructure locations.
My academy workSources and further help
- Virginia Business Ready Sites Program Site Characterization Guidelines, updated July 2026
Virginia Economic Development Partnership. Public guidance on characterization reports, due diligence, utilities, access, development constraints, and review of tier status. It supplies a research framework without certifying Red Onion or establishing grant eligibility.
- Assessing Brownfield Sites
United States Environmental Protection Agency. Public fact sheet explaining professional site assessment, Phase I review, and potential Phase II investigation. Its brownfields context does not establish that Red Onion is contaminated or is a brownfield.
Guidance may change. Follow the current source and check the software version, license, local rules and data limitations before applying the method.